MICA CREEK
APIP completed the construction of a double circuit spun concrete pole line. APIP faced challenging ground conditions with hard rocky conditions on site – tackled successfully by our machinery and experienced operators. Night works were performed in the tension stringing of the line to minimise impact to other construction works on site. The completion of this line is another key milestone in the solar farm commissioning.

UGL Renewables